Michilis Pty Limited have been actively working on Flynn's Beach Seawall since early May 2019 - 

Consisting mainly of heavily reinforced concrete this seawall will support the Flynn's Beach Promenade for many years to come.

Michilis proposed an alternate construction method to original design concept, which also provided Port Macquarie Hastings Council with a superior product that still meets aesthetic requirements.

By proposing a more robust reinforced concrete retaining wall (Than originally designed) Michilis enabled the removal of costly rock anchoring & also reduced overall project construction time frame.

Please see above gallery of progression site photos of the Flynn's Beach Seawall.